QUESTION |
ANSWER |
|
Who can I call about asbestos removal or
demolition questions? |
AQMD Asbestos Hot Line at
(909) 396-2336
Tuesday–Friday, 7:00 am – 5:00 pm
|
|
Do I have to have a survey before I send
a demolition form to AQMD? |
YES
|
|
Who needs to file the Asbestos Removal
or Demolition Notification forms?
Who should fill out the notification?
|
CONTRACTORS
-
The Contractors that will remove asbestos and/or
demolish the structure.
-
Notifications should be completed, signed, paid, and
mailed by the contractor performing the removal and/or demolition
project.
|
|
Are there exceptions to the Notification
form process? |
YES
-
Asbestos removals of less than 100 square feet.
-
Renovations without asbestos.
-
Other Rule requirements may apply.
|
|
Are homeowners required to file a
Notification form? |
YES
-
Only when performing a demolition by owner.
-
This exemption applies only to the owner of the house who is a
permanent resident of this house.
-
Other Rule requirements may apply.
|
|
Where can I find asbestos demolition
notification forms and fee information? |
At AQMD web site:
-
http://www.aqmd.gov
-
Click on “Business”
-
Click on “Compliance Program”
-
Click on “Asbestos Removal & Demolition”
|
|
Where do I send my completed asbestos
demolition or notification form? |
SCAQMD Asbestos Notifications
File #55641
Los Angeles, CA 90074-5641
Keep a copy of your notification
for your records and to
obtain
a city demolition permit. |
|
Do I need an AQMD demolition permit or
an asbestos permit? |
NO
|
|
Are there due dates for the Notification
and fee? |
YES
|
|
How is the notification fee determined? |
SIZE OF PROJECT IN SQUARE FEET
-
Removals require a fee based on the amount of
asbestos to be removed.
-
Demolitions require a fee based on the building
size.
-
Refinery and/or chemical unit demolition fees are
based on the structure’s footprint surface area.
|
|
What are the notification fees and where
do I find them? |
Fees
are specified in AQMD
Rule 301, Table VI. They are usually updated annually as
of July 1.
|
|
I want to hand carry my Notification to
AQMD |
We strongly recommend that you mail the notifications to save time
and money, and to reduce traffic and air pollution. However, you
can drop the notification in the inbox labeled “Asbestos
Notifications” located at the cashier’s window in the lobby at
AQMD’s Diamond Bar Headquarters. |
|
Can I submit my notification without
fees? |
NO
|
|
Do I need
to notify AQMD if I am doing a “soft” demolition?
|
NO
|
|
What is the
purpose of the 14 day waiting period?
Why do I
have to wait 14 calendar days?
|
INSPECTION
|
|
When can I
expect an inspector at my site before, or during
abatement/demolition?
|
ANY TIME
-
Any time before, during, and/or after
renovation/demolition completion, an inspector may visit your
site.
-
Inspectors verify compliance, observe asbestos
removal procedures, and confirm that the asbestos was removed
prior to demolition or renovation.
|
|
Do I have
to notify for a demolition if there is no asbestos?
What if I
know there is no asbestos?
|
YES
|
|
Can anybody
remove asbestos from a building if there is less than 100 square
feet of asbestos present?
As a
demolition contractor, can I remove asbestos if it is under 100 Sq
Ft?
|
NO
|
|
Do I have to remove non-friable asbestos before I can
demolish a building?
|
YES
|
|
Do you
offer financial assistance for asbestos removal? |
NO
|
|
Is there
any way I can do the demolition before the 14 calendar-day
elapsed? |
NO, except that
-
Court-ordered demolitions with proof of a written
court order, an asbestos survey, and confirmation that all the
asbestos was removed, may be eligible to submit an Ordered
Demolition Notification.
|
|
The city
B&S told me I need to call you regarding the demolition permit.
Is that true? |
YES
|
|
Does AQMD
send a letter to me or the city verifying that my notification has
been received and my demolition permit can be issued? |
NO
|